建筑业企业取得《建筑工程施工许可证》后,办理变更、延续、注销需在规定期限内向主管部门申报,动态监管包括哪些内容?( )
A.The permit must be obtained from the local housing and urban‑rural development bureau.
B.Changes, extensions, or cancellations of the construction permit must be reported within 30 days after the change occurs.
C.Dynamic supervision includes annual review, change filing, and reporting of major events.
D.The authority may order rectification or cancellation of the qualification if violations occur.
E.Qualifications can be granted solely based on industry self‑regulation without government approval.
优质解答
答案
BCD
解析
正确选项为B、C、D。B说明变更须在30天内报告,C说明动态监管的核心内容,D说明违规可被监管机关整改或注销。A、E均为错误表述,分别夸大审批方式和忽视政府监管。
科目:法规题型:多选题难度:中等来源:AI生成